Central Avenue Rebuild Project Water Service Update

The Municipality of Inverness County is advising that as part of the Central Avenue Rebuild Project, there are no planned water service disruptions for Wednesday, Nov. 18 and Thursday, Nov. 19. There will be a water service disruption on Friday, Nov. 20 for a small section of the community. Further details can be found below.

There are no other additional water service interruptions planned in connection with Phase One project work. With any existing water distribution system however, unexpected service interruptions may still occur outside of the project area due to the aging condition of the existing infrastructure.

This week’s work represents a major milestone for the project and will complete the water system work associated with Phase One.

What to Expect for the Remainder of the Week:

Wednesday, November 18 & Thursday, November 19

Water Service: No planned disruptions.

During these two days, the contractor will continue connecting residences within the construction area to the new water system. Residents along Central Avenue within the construction area can continue using their water as usual, but may notice short, individual service interruptions as the contractor switches their services over to the new line.

Friday, November 20: Temporary Water Service Disruptions

On Friday, sections of the water distribution system must be temporarily isolated to complete the final disconnection work from the old system.

What residents need to know:

  • Residents in the following areas will experience a temporary loss of water service beginning at approximately 7:30 a.m.:
    • Central Avenue, civic addresses 15697 to 15798
    • Park Street
    • Bonnie Brae Street
    • Amy Lane
    • Beach Road No. 1
  • All users of the Inverness water distribution system may notice reduced water pressure throughout the day as staff temporarily slow the flow of water to safely complete the work.
  • Water service is expected to be restored during the evening.

How to Prepare

Residents in the affected areas are encouraged to plan ahead for Friday’s temporary water service interruption by:

  • Filling containers with enough drinking water to meet household needs throughout the day.
  • Filling a bathtub with water to use for flushing toilets.

What’s Next?

  • In the coming weeks, the contractor will:
    • Install stormwater infrastructure (includes catch basins, storm pipes, storm manholes, and culverts, designed to keep stormwater out of the sanitary sewer). Residents may have noticed the large black pipes currently placed alongside the construction area. These pipes will form part of the upcoming stormwater work.
    • Install a new lift station (moves wastewater from lower to higher ground so it can reach treatment plants) near the Shean Trail Crossing.
    • Dig up the road for a new road base.

The Municipality understands that residents value reliable water service and recognizes the inconvenience that construction-related disruptions can cause. While work on the project will continue, completing the water connections is an important step forward.

Stay Informed

There are several ways to stay up to date about the project.

  • Email updates: Sign up here to receive project updates directly in your inbox.
  • Project Information Centre: Residents are welcome to drop in and speak directly with a municipal representative at the Project Information Centre.
    • Location: Inverness Fire Hall, 15797 Central Ave., Inverness
    • Hours: 1 p.m. to 4 p.m.
    • Upcoming dates:
  • Tuesday, November 24
  • Tuesday, December 1
  • Tuesday, December 8
  • Tuesday, December 15

Please note that hours are subject to change. Residents are encouraged to check here for updates before visiting.

The Municipality sincerely thanks residents for their continued patience, understanding and cooperation.  Infrastructure improvements can bring short-term inconveniences, and the Municipality remains committed to keeping the community informed as work progresses.

More News

Nov. 17 Water Main Tie-Ins & Service Disruptions

November 16, 2026

November 17 Water Main Tie-Ins & Service Disruptions | Inverness Water Disruptions A second set…

Council Adopts New Bylaws

November 16, 2026

Municipal Council Adopts New Bylaws 67, 68 and 69 As part of an ongoing bylaw…

Inverness Water Disruption | November 16

November 15, 2026

Central Avenue Rebuild Update | Water Main Tie-Ins & Service Disruptions As part of the…