A wastewater lift station is being replaced in Port Hood. A wastewater lift station is a pressurized system that moves sewer from lower to higher elevations. Installed in the 1970s, this lift station is at its end of useful life cycle. Replacing the lift station will improve the efficiency and reliability of sewage handling in the area, reduce the risk of environmental incidents and ensure compliance with regulatory requirements.
Location:
The lift station is located at the intersection of Main Street and Convent Street, Port Hood.
Project Timeline:
Spring to mid-Summer 2026
What to Expect During Construction
Most work will take place off the roadway; however, there is a section of work that will cause a reduction to one lane of traffic. Traffic control will be on site during that time.
There will be no planned interruption to municipal wastewater services throughout the duration of this project.
Construction Hours:
Construction work will be conducted during the following hours:
- Monday to Friday, 6 a.m. – 6 p.m.
- Please note, work hours may vary depending on weather and other unforeseen circumstances.
Noise and traffic:
- There will be minimal impact to the surrounding area. Light construction noise may be noticeable during work hours.
- At times, traffic control measures will be in place. Any detours will be clearly marked.
Safety Concerns:
- Public safety is our priority, please use caution around the construction zone.
- Access to the construction site is strictly prohibited. Unauthorized individuals are prohibited from entering the site for safety reasons.
- Please follow all signage and detour routes if needed.
Project specifics:
- Design Engineer: Strum Consulting
- Tender Identification Number: MCI -TEN -2025- 006
- Contractor: Zutphen Contractors Inc.
Environmental Impacts and Regulatory Compliance
This project will be completed in accordance with applicable provincial and federal environmental regulations. Environmental protection measures will be in place throughout the construction process to minimize any impacts.
Budget
This project represents an investment of $1,482,075, with 50% covered by the municipality’s capital budget, and the remaining 50% covered by the Nova Scotia Growth and Renewal for Infrastructure Development (GRID) Program.
Acknowledgement of Challenges:
The Municipality of Inverness County acknowledges that this is a challenging time for public-facing projects due to supply chain disruptions, market fluctuations, and contractor availability. While we strive to provide the most accurate information, please understand that project timelines, costs, and other details are subject to change. We will keep the public informed with updates as they become available.
Contact Us:
If you have any questions or concerns, please feel free to reach out:
- Email construction@invernesscounty.ca
- Call toll-free 1-866-258-0223, select option #0.
For More Information
Port Hood Wastewater Lift Station Replacement Kicks Off April 27