Port Hood Lift Station Replacement Update
Work continues on the replacement of the Port Hood Wastewater Lift Station, located at the corner of Main St. and Convent St., Port Hood
Over the past two weeks, crews have excavated trenches, assembled and installed piping, and connected the new infrastructure to the lift station system. This phase of the project is anticipated to be completed next week (June 22–26). Once this work is finished, the roadway will be graded and the area cleaned up.
Construction activities will then shift back to the lift station site.
Intermittent traffic control measures will remain in place on a portion of Main St. (in front of 375 Main St.), reducing traffic to a single lane for the duration of the project.
Motorists can expect minimal delays; however, they are encouraged to allow extra travel time when travelling through the area. Should the project schedule require additional time, an update will be provided.
The Municipality thanks residents and motorists for their patience and cooperation throughout this work.
To learn more about the Port Hood Lift Station Replacement Project, visit Port Hood Wastewater Lift Station Replacement | Municipality of the County of Inverness .
More News
Beach Bingo 2026
June 18, 2026
Beach Cleanup Bingo Returns this July The Municipality of Inverness County is excited to announce…
June Feedback Loop
June 18, 2026
June Feedback Loop Survey Focuses on the Environment The Municipality of Inverness County is launching…
Whycocomagh Boil Water Advisory Lifted – June 12, 2026
June 12, 2026
The Municipality of Inverness County would like to notify users of the Whycocomagh water system…

